Which statement best describes actions when TCPI is greater than 1 and indicates future performance must improve to meet the plan?

Prepare for the Landini CAPM exam with this comprehensive quiz. Study with flashcards and multiple choice questions, accompanied by detailed explanations and hints. Be ready for your certification!

Multiple Choice

Which statement best describes actions when TCPI is greater than 1 and indicates future performance must improve to meet the plan?

Explanation:
TCPI, the To-Complete Performance Index, shows how efficiently the remaining work must be done to finish the project within the budget. It compares the work left to the funds left under the chosen baseline. When TCPI is greater than 1, you must improve performance beyond what you’ve been delivering so far to meet the plan. If it’s exactly 1, you’re on target at the current pace; if it’s less than 1, you can continue with less intensity or you have some budget cushion. So, when TCPI exceeds 1, the statement that best describes the situation is that future performance must surpass the current performance to meet the plan. For example, using the original plan, if BAC is 100k, EV is 60k, and AC is 70k, TCPI would be (100−60)/(100−70) = 40/30 ≈ 1.33, meaning you’d need to complete remaining work at about 133% of the planned rate to stay on budget. This isn’t about finishing ahead of schedule or about no change; it’s about needing higher efficiency to stay within budget. It also isn’t a judgment about remaining value vs funds; it’s a measure of performance pace required to meet the plan.

TCPI, the To-Complete Performance Index, shows how efficiently the remaining work must be done to finish the project within the budget. It compares the work left to the funds left under the chosen baseline. When TCPI is greater than 1, you must improve performance beyond what you’ve been delivering so far to meet the plan. If it’s exactly 1, you’re on target at the current pace; if it’s less than 1, you can continue with less intensity or you have some budget cushion.

So, when TCPI exceeds 1, the statement that best describes the situation is that future performance must surpass the current performance to meet the plan. For example, using the original plan, if BAC is 100k, EV is 60k, and AC is 70k, TCPI would be (100−60)/(100−70) = 40/30 ≈ 1.33, meaning you’d need to complete remaining work at about 133% of the planned rate to stay on budget.

This isn’t about finishing ahead of schedule or about no change; it’s about needing higher efficiency to stay within budget. It also isn’t a judgment about remaining value vs funds; it’s a measure of performance pace required to meet the plan.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy