Which metric indicates the rate at which the project budget is being spent?

Burn rate

The burn rate measures how fast the project budget is being spent, typically expressed as amount spent per month. It shows the pace of spending and helps forecast how long the budget will last. For example, with a $1,000,000 budget and $200,000 spent after two months, the burn rate is $100,000 per month, which lets you estimate remaining runway by dividing the remaining budget by the burn rate. The other metrics describe different performance aspects: cost variance is the difference between planned and actual costs, cost performance index compares earned value to actual cost to indicate cost efficiency, and schedule variance compares earned value to planned value to indicate schedule performance. None of these directly capture the rate of spending, which is what the burn rate does.

Cost Variance

Cost Performance Index

Schedule Variance

Want more questions?

All options are one-time payments.

$12.50

30 day premium pass

All the basics to get you started

  • Ad-free experience
  • View your previous attempt history
  • Mobile app access
  • In-depth explanations
  • 30 day premium pass access
$30.00 $87.50 usd

6 month DELUXE pass (most popular)

Everything with the 30 day premium pass FOR 6 MONTHS! & the ultimate digital PDF study guide (BONUS)

  • Everything included in the premium pass
  • $87.50 usd value for $30.00! You save $57.50!
  • + Access to the ultimate digital PDF study guide
  • + 6 months of premium pass access
  • + Priority support
$12.50 $18.99

Ultimate digital PDF study guide

For those that prefer a more traditional form of learning

  • Available for instant download
  • Available offline
  • Hundreds of practice multiple choice questions
  • Comprehensive content
  • Detailed explanations
Image Description
Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy