If material costs budgeted at $10,000 are reduced by 10%, saving $1,000, and Schedule Variance is zero, what is the Cost Variance?

Prepare for the Landini CAPM exam with this comprehensive quiz. Study with flashcards and multiple choice questions, accompanied by detailed explanations and hints. Be ready for your certification!

Multiple Choice

If material costs budgeted at $10,000 are reduced by 10%, saving $1,000, and Schedule Variance is zero, what is the Cost Variance?

Explanation:
Cost Variance shows whether the project is under or over budget, calculated as Earned Value minus Actual Cost (CV = EV − AC). Since Schedule Variance is zero, the work completed has the same value as planned, so EV equals PV. The material budget is 10,000, and reducing costs by 10% means the Actual Cost is 9,000. With EV on the same level as PV at 10,000, CV = 10,000 − 9,000 = 1,000. This positive value indicates a favorable, under-budget result. The other options don’t fit because they require different EV or AC values than provided; for example, a zero CV would need EV and AC to be equal, which isn’t the case here, and a negative or 9,000 CV would imply different relationships between EV and AC.

Cost Variance shows whether the project is under or over budget, calculated as Earned Value minus Actual Cost (CV = EV − AC). Since Schedule Variance is zero, the work completed has the same value as planned, so EV equals PV. The material budget is 10,000, and reducing costs by 10% means the Actual Cost is 9,000. With EV on the same level as PV at 10,000, CV = 10,000 − 9,000 = 1,000. This positive value indicates a favorable, under-budget result. The other options don’t fit because they require different EV or AC values than provided; for example, a zero CV would need EV and AC to be equal, which isn’t the case here, and a negative or 9,000 CV would imply different relationships between EV and AC.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy